JOB

Final Client

Telica Client

ABB Spa

Type of Plant

FERTILIZER PLANT

Final destination

MAROCCO

Technology

ABB INDUSTRIAL-IT

Scope of Work

HW and SW Engineering, Cabinets Manufacturing, Commissioning

I/Os number

4000

Number of Cabinets

80 Control Cabinets

Telica’s involved manpower

8

Total number of worked hours

9000

Year

2013, 2014

Telica Client

HONEYWELL

Type of Plant

REFINERY

Final destination

KUWAIT

Technology

HONEYWELL C300 SAFETY MANAGER

Scope of Work

HW and SW Engineering Document Controller, Cabinets and Consoles Manufacturing, Commissioning

I/Os number

75000

Number of Cabinets

150 Control Cabinets 60 Operator Consoles

Telica’s involved manpower

20

Total number of worked hours

60000

Year

2016, 2017, 2018

Telica Client

HONEYWELL

Type of Plant

AMMONIA UREA

Final destination

GUBAKHA RUSSIA

Technology

HONEYWELL C300 SAFETY MANAGER

Scope of Work

HW and SW Engineering, Cabinets Manufacturing

I/Os number

15000

Number of Cabinets

195 Control Cabients

Telica’s involved manpower

15

Total number of worked hours

16500

Year

2018, 2019

Telica Client

LEONARDO

Type of Plant

Parcel-Sorting Facilities

Final destination

DERBY UK

Technology

SIEMENS CPU SERIE 1500 ET200 SP

Scope of Work

HW and SW Engineering, Cabinets Manufacturing

I/Os number

8000

Number of Cabinets

80 Control Cabinets, 60 Electrical Cabinets

Telica’s involved manpower

12

Total number of worked hours

15000

Year

2018, 2019

Telica Client

LEONARDO

Type of Plant

Baggage Conveyor Belts

Final destination

PAKISTAN

Technology

SIEMENS CPU SERIE 300/400 ET200 SP

Scope of Work

HW and SW Engineering, Cabinets Manufacturing

I/Os number

10000

Number of Cabinets

125 Control Cabinets

Telica’s involved manpower

12

Total number of worked hours

11000

Year

2016, 2017

Telica Client

LEONARDO

Type of Plant

PANAMA CHANNEL

Final destination

PANAMA

Technology

ROCKWELL RS LOGIC 5000

Scope of Work

HW and SW Engineering

I/Os number

90000

Number of Cabinets

300 Control Cabinets

Telica’s involved manpower

20

Total number of worked hours

30000

Year

2014, 2015, 2016

SECTORS

Infrastructure

• Airports: control and monitoring systems for conveyor belts

• Undergrounds: traffic control and security systems

• Maritime channels: maritime traffic supervision system

Oil&Gas

• On-off shore plants

• Filtration and treatment plants

• Skid

Chemical and Petrochemical

• Fertilizer production plants

• LNG plants

Ecology

• Air quality supervision plants

• Smoke control systems

• Water purification plants

Power

• Automation systems for power plants

• Plants for Renewable Energy

Materials handling

• Monitoring and control of baggage transport belts for airports

CASE HISTORY

THE IRANIAN CHALLANGE

In 2018, after years of collaboration and important objectives achieved, Telica is identified as Honeywell’s ideal partner to live together one of the most significant challenges in the sector in recent years.

TARGET

Collect at the facility all the ongoing projects acquired in the year 2017 by Honeywell with destination IRAN, test them and organize their shipment by the latest date of November 4, 2018 after which the American embargo imposed on Iran, would have prohibited them the shipment

IRANIAN PROJECTS ENTRUSTED TO TELICA

  • South Pars Gas Field
  • Tabriz Oil Refinery
  • Hengam Oil&Gas
  • Bid Boland Gas Plant
  • Kangan LNG Oil&Gas
  • Jam Pet Petrochemical

NUMBERS

  • 480 control, servers, network and distribution cabinets
  • 150.000 hardwired signals
  • 60 involved engineers, technicians, electricians, managers
  • 3.000 sq.m among offices and workshop area
  • 100.000 manhours
  • 600 Seaworthy packaging for cabinets and cables
  • 30 arranged transports
  • 80 KW power supply availability for cabinets feeding

ACTIVITIES CARRIED OUT

  • Loading & Unloading of the goods
  • Seaworthy Packing & Unpacking
  • Cabinets and consoles handling and disposition in the workshop area
  • Power supply cabinets feeding and system network interconnection
  • Functional tests of all the cabinets and consoles and issue of the relevant test certifications
  • People coordination and management, including hotel/apartments booking, shuttle services from/to airport/hotel and canteen service

OUTCOMES
Thanks to the strong collaboration between all the involved companies, but above all thanks to the great human value put in place, the scope has been achieved with great satisfaction of the Customer